The soft starting of motor circuits is the process of limiting inrush current and mechanical shock during startup by gradually ramping up the stator voltage. Unlike across-the-line (DOL) starting, which slams the motor with full line voltage and draws 600% to 800% of Full Load Amps (FLA), a solid-state soft starter uses back-to-back thyristors (SCRs) on each phase to chop the voltage waveform, increasing the RMS voltage over a programmable ramp time (typically 2 to 15 seconds).
If you are specifying a drive for a new conveyor, pump, or fan, the direct answer for sizing is this: size the soft starter at 1.25x to 1.5x the motor FLA for standard centrifugal loads, and 2.5x to 3.0x the motor FLA for high-inertia or high-breakaway-torque loads. Always base your selection on the motor's nameplate FLA and the specific load profile, never just the horsepower rating.
Sizing Rules and Worked Load Examples
Horsepower and kilowatt ratings are useless for sizing motor controls without load context. A 10 HP motor driving a centrifugal water pump behaves entirely differently than a 10 HP motor driving a loaded rock crusher. The soft starter must be sized to handle the thermal stress of the starting current over the duration of the ramp.
Worked Example: 15 HP, 460V, 3-Phase AC Induction Motor
- Motor Nameplate FLA: 21 Amps
- Scenario A (Centrifugal Pump): Low breakaway torque, ramps up in 4 seconds.
Sizing: 21A × 1.5 = 31.5A. Select a standard 32A or 38A soft starter. - Scenario B (Loaded Belt Conveyor): High breakaway torque, requires a 12-second ramp to prevent belt snapping.
Sizing: 21A × 3.0 = 63A. Select a 65A or 72A heavy-duty soft starter with an integrated bypass contactor.
Motor Type Comparison and Controller Demands
Not all motors accept soft starting. Solid-state reduced-voltage starters are designed almost exclusively for standard AC squirrel-cage induction motors. Treating different motor architectures as interchangeable is a fast track to bricked equipment.
| Motor Type | Torque Curve & Inrush | Control / Driver Demands | Relative Cost |
|---|---|---|---|
| AC Induction (Squirrel Cage) | High inrush (6-8x FLA); torque proportional to voltage squared. | Ideal for soft starters or VFDs. Requires 3-phase SCR firing. | Low (Motor) / Medium (Drive) |
| Wound Rotor Induction | Low inrush; high starting torque via external rotor resistance. | Requires slip rings and external resistor banks. Do not use solid-state soft starters. | High (Motor & Maintenance) |
| Synchronous AC | Complex starting; requires amortisseur winding and DC field excitation. | Demands specialized synchronous VFDs or across-the-line with excitation controllers. | Very High |
| Stepper / Servo (DC/BLDC) | Precise position/speed control; inrush managed by driver microstepping. | Requires dedicated step/direction or FOC (Field Oriented Control) drives. Never use AC soft starters. | High (Drive complexity) |
For 95% of industrial and commercial applications involving fans, pumps, compressors, and conveyors, the AC Induction (Squirrel Cage) motor paired with a solid-state soft starter is the correct, most cost-effective fit. For deeper technical specifications on motor classifications, refer to the NEMA MG 1 standard for Motors and Generators.
Wiring, Terminals, and Failure Signatures
Wiring a soft starter incorrectly will result in immediate catastrophic failure or nuisance tripping. Modern units feature two primary power wiring topologies: Inline (standard) and Inside-Delta (which allows a smaller, cheaper starter to be used by placing the SCRs inside the motor's delta winding, but requires a 6-lead motor).
Standard Inline Terminal Identification
| Terminal Label | Function | Wiring Note |
|---|---|---|
| 1/L1, 3/L2, 5/L3 | Line Input (Mains) | Connect from the upstream disconnect/fuse block. |
| 2/T1, 4/T2, 6/T3 | Load Output (Motor) | Connect directly to the motor U, V, W terminals. |
| A1, A2 / 13, 14 | Control Voltage / Start | 13/14 is typically the NO start contact; A1/A2 is the 120V/24V coil supply. |
| B1, B2 / K1, K2 | Bypass Contactor Coil | Energizes the mechanical contactor to shunt the SCRs once at full speed. |
Diagnosing Failure Signatures
When a soft starting of motor setup fails, the physical symptoms on the jobsite point directly to the root cause:
- The "Hum" and Vibration (Single Phasing): If the motor emits a loud 120Hz hum and vibrates violently without rotating, one of the internal SCRs has likely failed open, or a line fuse has blown. The motor is receiving single-phase power. Fix: Test across L1-L2, L2-L3, and L1-L3 for continuity and balanced voltage.
- Overheating and Thermal Trip: If the soft starter trips on "Thermal Overload" during the ramp, the ramp time is set too long for the starter's thermal mass, or the bypass contactor is failing to engage. SCRs generate roughly 1.5W of heat per ampere per phase. Without a bypass contactor taking over at 100% voltage, that heat will melt the silicon. Fix: Verify bypass engagement and check the ramp time parameter.
- Stall or "Lugging": The motor slowly turns but cannot reach synchronous speed, drawing massive current and eventually tripping. This happens when the Initial Torque (or pedal voltage) parameter is set too low. If the load requires 35% breakaway torque, but the soft starter is programmed to begin its ramp at 20%, the motor will stall until the ramp voltage catches up. Fix: Increase the initial torque setting in 5% increments until the load breaks away smoothly.
Soft Starting of Motor FAQ
What is the difference between soft starting of motor circuits and using a VFD?
A soft starter only controls the motor during acceleration and deceleration. It limits current by reducing voltage but does not change the frequency (Hz). Once the motor reaches full speed, the soft starter bypasses itself, and the motor runs directly on the 60Hz (or 50Hz) line. A Variable Frequency Drive (VFD), on the other hand, continuously controls both voltage and frequency, allowing for precise speed control, holding torque at zero speed, and continuous energy savings on variable torque loads. Choose a soft starter if you only need to protect the mechanical drivetrain from startup shock and prevent voltage sags on the grid. Choose a VFD if the process requires the motor to run at varying speeds. For a detailed breakdown of starter types, The Engineering Toolbox provides an excellent comparison of electrical motor starters.
Is soft starting of motor systems viable for single-phase AC loads?
Generally, no. True solid-state soft starters rely on manipulating three-phase waveforms and require a rotating magnetic field to function correctly. Single-phase motors (like PSC or split-phase compressor motors) use start capacitors and centrifugal switches that will violently clash with SCR phase-angle firing, often destroying the start winding or the soft starter itself. For single-phase inrush mitigation, you should use a hard-start kit (a properly sized start capacitor with a potential relay) or a dedicated single-phase variable voltage autotransformer, rather than a standard 3-phase soft starter.
Why does my soft starting of motor configuration still trip the main breaker?
If your upstream breaker trips during the ramp, you are likely dealing with a magnetic trip (instantaneous short-circuit protection) rather than a thermal overload. Soft starters still draw 300% to 450% of FLA during the ramp (compared to 600%+ across-the-line). If your upstream breaker is a standard thermal-magnetic molded case circuit breaker (MCCB) with a low magnetic trip setting (e.g., 5x to 10x In), the soft starter's reduced inrush might still exceed the breaker's instantaneous magnetic threshold. The fix: Ensure the upstream breaker is sized correctly for the motor FLA (typically 1.25x to 1.5x FLA per NEC 430.52) and, if adjustable, set the instantaneous/magnetic trip dial to at least 8x or 10x the breaker frame rating to allow the soft start ramp to complete without tripping the magnetic latch.
Do I need an isolation contactor upstream of the soft starter?
Yes. Soft starters are not approved as motor disconnects because the SCRs can leak current or fail in a closed state even when the control signal is removed. NEC and IEC standards require a physical air-gap disconnect (like a fused rotary disconnect or a mechanical isolation contactor) upstream of the soft starter to ensure the motor is truly de-energized for maintenance. Many modern soft starter panels integrate this isolation contactor into a single "combination" enclosure to save panel space.






