Subpanel wire size refers to the specific American Wire Gauge (AWG) or kcmil cross-sectional area of the feeder conductors required to safely carry the calculated electrical load from a main panel to a secondary distribution panel without exceeding temperature limits or causing excessive voltage drop. Getting this right dictates your maximum safe current capacity (ampacity), the physical conduit diameter you must pull through, and whether your voltage drop stays under the recommended 3% threshold for feeders. In residential and light commercial wiring, undersizing these feeders leads to overheated lugs, nuisance tripping, and dimming lights, while grossly oversizing them wastes money and makes physical termination nearly impossible.

Safety & Code Caveat: Working inside electrical panels involves lethal mains voltage. Always de-energize the main breaker, verify the busbars are dead with a tested non-contact voltage meter and a multimeter, and use lockout/tagout procedures. The sizing guidance below follows NEC-style principles; your local Authority Having Jurisdiction (AHJ) has final authority on all installations.

The Core Variables: Ampacity, Temperature Columns, and Distance

To determine the correct subpanel wire size, you must navigate the National Electrical Code (NEC) Table 310.16. The most critical concept here is the temperature column. Even if you pull THHN/THWN-2 wire (which is rated for 90°C), NEC 110.14(C) mandates that you must size the wire based on the lowest temperature rating of any connected termination, device, or conductor. Since the vast majority of residential breakers and panel lugs are rated for 75°C, you must use the 75°C column for your ampacity calculations, reserving the 90°C column strictly for derating adjustments (like ambient temperature or conduit fill).

Think of wire gauge like highway lanes: pushing 100 amps through a wire sized for 60 amps is like forcing rush-hour traffic onto a single-lane road—the resulting friction generates destructive heat that degrades the insulation and melts terminal lugs.

Standard Subpanel Feeder Wire Sizes (75°C Column, 3-Conductor + Ground)
Subpanel Breaker Size Copper Wire Size (THHN/THWN-2) Aluminum Wire Size (XHHW-2 / THHN) Minimum Copper EGC (Ground)
60 Amp 6 AWG 4 AWG 10 AWG
100 Amp 3 AWG 1 AWG 8 AWG
125 Amp 2 AWG 1/0 AWG 6 AWG
150 Amp 1 AWG 2/0 AWG 6 AWG
200 Amp 2/0 AWG 4/0 AWG 4 AWG

Note: EGC (Equipment Grounding Conductor) sizes are based on NEC Table 250.122. Aluminum feeders are highly cost-effective for long runs but require careful termination to prevent oxidation and thermal expansion issues.

Worked Numeric Example: Sizing a 100A Detached Garage Feeder

Let’s walk through a real-world scenario. You are feeding a 100A subpanel in a detached garage located 150 feet from the main house panel. The system is 240V single-phase. You plan to use copper THHN/THWN-2 conductors in PVC conduit.

Step 1: Base Ampacity Sizing
Looking at the 75°C column in Table 310.16, a 100A load requires a minimum of 3 AWG Copper (rated 100A at 75°C).

Step 2: Voltage Drop Calculation
The NEC recommends a maximum 3% voltage drop for feeders to ensure equipment operates efficiently. We use the standard single-phase voltage drop formula: VD = (2 × K × I × D) / CM.

  • K (Specific resistance for Copper) = 12.9 ohms per mil-foot
  • I (Current) = 100 Amps (worst-case full load)
  • D (Distance) = 150 feet
  • CM (Circular Mils for 3 AWG) = 52,620

VD = (2 × 12.9 × 100 × 150) / 52,620
VD = 387,000 / 52,620 = 7.35 Volts

Step 3: Evaluate the Drop
Percentage Drop = (7.35V / 240V) × 100 = 3.06%.
This slightly exceeds the recommended 3% threshold. While technically legal under the NEC (which only mandates voltage drop for specific sensitive loads or feeders over 1000ft in some local amendments), best practice dictates upsizing to ensure welders, compressors, and EV chargers in the garage get adequate voltage.

Step 4: Upsize and Recalculate
We step up to 2 AWG Copper (CM = 66,360).
VD = 387,000 / 66,360 = 5.83 Volts.
Percentage Drop = (5.83V / 240V) × 100 = 2.43%. This passes the 3% rule comfortably.

The Verdict: For a 150-foot run to a 100A subpanel, pull 2 AWG Copper (or 1/0 Aluminum) for the hots and neutral, and an 8 AWG Copper equipment grounding conductor.

Where You Meet This in Practice

Theory only gets you to the supply house; practice gets the panel energized. When you are actually pulling these wires and terminating them, three physical realities dictate your success.

1. Conduit Fill and Physical Pulling
You cannot just stuff wires into a pipe. NEC Chapter 9, Table 1 limits conduit fill to 40% for three or more conductors. For our 100A garage example (two 2 AWG hots, one 2 AWG neutral, one 8 AWG ground), the cross-sectional area of the wires requires a minimum of 1-inch Schedule 40 PVC conduit. If you try to force 2 AWG THHN into 3/4-inch PVC over a 150-foot run with sweeps, you will likely damage the insulation or injure your back. Use 1-inch or even 1.25-inch PVC to make the pull manageable, and always use wire pulling lubricant.

2. Torque Specifications (NEC 110.14(D))
Since the 2017 NEC cycle, you are legally required to use a calibrated torque tool to tighten breaker and lug connections to the manufacturer’s specified inch-pounds. A 100A Square D QO or Homeline main breaker lug typically requires between 40 and 50 in-lbs of torque. Under-torquing causes high-resistance connections that arc and melt; over-torquing strips the aluminum wire or damages the lug threads.

3. What People Commonly Confuse It With
The most frequent mistake DIYers and junior apprentices make is confusing the subpanel’s main disconnect breaker size with the feeder wire’s ampacity. It is entirely legal to feed a subpanel that has a 100A main breaker using 60A wire, provided the upstream breaker in the main panel is also 60A (the upstream breaker protects the wire). Conversely, it is a massive fire hazard to feed a 60A rated subpanel busbar with 100A wire protected by a 100A upstream breaker. The wire might survive, but the panel busbars will overheat. Always match the upstream breaker to the wire ampacity, and ensure the subpanel’s busbar rating is equal to or greater than the upstream breaker.

Another common confusion is relying on the 90°C column for THHN wire. Because the wire jacket says 90°C, builders assume they can use 4 AWG THHN (rated 95A at 90°C) for a 100A feeder. This is a direct violation of NEC 110.14(C) because the breaker lugs are only rated for 75°C. You must use 3 AWG (or 2 AWG for voltage drop).

FAQ: Subpanel Feeder Sizing Edge Cases

Do I need to isolate the neutral and ground in the subpanel?

Yes. For any subpanel, especially in a detached structure (NEC 250.32), you must run a 4-wire feeder (2 hots, 1 neutral, 1 ground). The neutral bar and ground bar in the subpanel must be physically isolated. Remove the green bonding screw or bonding strap that came with the panel. The neutral carries return current; the ground only carries current during a fault. Bonding them at the subpanel creates a parallel neutral path on the grounding system, which can energize metal enclosures and cause lethal shock hazards.

Can I use aluminum wire for a subpanel feeder?

Absolutely, and it is highly recommended for long runs to save money. According to the Copper Development Association and modern utility practices, aluminum is perfectly safe when installed correctly. Use XHHW-2 or THHN aluminum, ensure the lugs are rated for aluminum (most modern dual-rated lugs are marked CU/AL), and torque them precisely to spec. The old myth about aluminum causing fires stems from the 1970s when improper alloys and un-torqued connections were used; modern AA-8000 series aluminum alloy is stable and reliable.

Does the neutral wire need to be the same size as the hots?

For standard single-phase residential feeders, yes. While the NEC allows sizing the neutral smaller than the ungrounded (hot) conductors if the calculated neutral load is significantly lower (NEC 220.61), the practical reality of modern homes with 240V loads, EV chargers, and the minimal cost difference makes full-sized neutrals the standard. Furthermore, if you are upsizing the hots for voltage drop, the NEC requires you to upsize the neutral proportionally to maintain the impedance balance.

What if my main panel doesn't have space for a 100A breaker?

If your main panel is maxed out on physical spaces, you cannot simply squeeze in a 100A feeder breaker. You must either install a subpanel off the main to create space, or use a "feed-through" lug if your main panel supports it. Never double-tap a breaker lug unless the breaker is explicitly listed and marked for two conductors (which is rare for large gauge feeder wire).